SUP 5252.237-9400 Substitution Or Addition Of Personnel (JAN 1992). Insert the following clause in cost reimbursement, time and material and labor hour solicitations and contracts when personnel requirements are used as one of the evaluation factors for award. The Contracting Officer shall insert the following: (*) a check indicating that personnel substituting shall not occur during the entire performance period; or (**) the number of days, if such time is less than the entire performance period.
SUP 5252.237-9400 SUBSTITUTION OR ADDITION OF PERSONNEL (JAN 1992)
- The offeror agrees to assign to the contract those persons whose resumes, personnel data forms or personnel qualification statements were submitted as required by Section L to fill the requirements of the contract. No substitution or addition of personnel shall be made except in accordance with this clause.
- The offeror agrees that:
- during the contract performance period
- during the first __ days of the contract performance period no personnel substitutions will be permitted unless such substitutions are necessitated by an individual's sudden illness, death or termination of employment. In any of these events, the Contractor shall promptly notify the Contracting Officer and provide the information required by paragraph (d) below.
- If personnel for whatever reason become unavailable for work under the contract for a continuous period exceeding thirty (30) working days, or are expected to devote substantially less effort to the work than indicated in the proposal, the Contractor shall propose a substitution of such personnel, in accordance with paragraph (d) below.
- All proposed substitutions shall be submitted, in writing, to the Contracting Officer at least fifteen (15) days (thirty (30) days if a security clearance must be obtained) prior to the proposed substitution. Each request shall provide a detailed explanation of the circumstances necessitating the proposed substitution, a complete resume for the proposed substitute and any other information required by the Contracting Officer to approve or disapproved the proposed substitution. All proposed substitutes (no matter when they are proposed during the performance period) shall have qualifications that are equal to or higher than the qualifications of the person being replaced.
- In the event a requirement to increase the specified level of effort for a designated labor category, but not the overall level of effort of the contract occurs, the offeror shall submit to the Contracting Officer a written request for approval to add personnel to the designated labor category. The information required is the same as that required in paragraph (d) above. The additional personnel shall have qualifications greater than or equal to at least one (1) of the individuals proposed for the designated labor category.
- The Contracting Officer shall evaluate requests for substitution and addition of personnel and promptly notify the offeror, in writing, of whether the request is approved or disapproved.
- If the Contracting Officer determines that suitable and timely replacement of personnel who have been reassigned, terminated or have otherwise become unavailable to perform under the contract is not reasonably forthcoming or that the resultant reduction of productive effort would impair the successful completion of the contract or the delivery order, the contract may be terminated by the Contracting Officer for default or for the convenience of the Government, as appropriate. Alternatively, at the Contracting Officer's discretion, if the Contracting Officer finds the Contractor to be at fault for the condition, he may equitably adjust (downward) the contract price or fixed fee to compensate the Government for any delay, loss or damage as a result of the Contractor's action.